Latest from Southwark Council on the Burbage resurfacing and road closures (dated 7 Feb)

Resurfacing of Burbage Road will take place between 11th and 21st February.

Work on Burbage Road, will be carried out in 4 stages. Traffic Marshals will be deployed to each Junction to monitor Traffic.

1)      Burbage Road jw Dulwich Village to Turney Road. Work will be carried out under road closure, between 11th Feb and 12th Feb 2013.

2)      Burbage Road jw Turney Road to Stradella Road.  Work will be carried out under road closure, between 13th Feb and 15th Feb 2013.

3)      Burbage Road jw Stradella Road to Half Moon Lane.  Work will be carried out under road closure, between 18th Feb and 20th Feb 2013.

4)      Table at Burbage Road jw Turney Road.  Work will be carried out under four-way traffic lights, between 20th Feb and 21st Feb 2013.

All existing humps will be replaced at same location with 100mm sinusoidal humps.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s